I was involved with off-grid stuff. So we'd aim to get the AC (the generator) as close to the battery & inverter as possible to minimise the (48v nominal) high current DC cabling. Then the distance from the power centre to the buildings would be 230vac - much cheaper, 5x less current.There and back?? That's not how inverters work.
The DC cabling requirment is smaller and cheaper as voltages are higher.
Means AC grid tied.
Not sure what that means but I think you're getting towards talking about hybrid inverters? That have capability to charge/discharge batteries and accept DC from PV. Neither of those inverters are hybrid ones.
Sorry to pick apart your post, it just, to me, reads as really confusing for the OP.
So... I was suggesting that the building mains could be taken out to the Solar Array, site the Inverter close to the Solar Array, and synch or AC Grid Tie there.
They weren't "Hybrid" inverters, but known as Inverter-Chargers - so yes they could Synch with an AC source and charge battery packs its a seamless changeover from battery supply to AC supply (& vice-versa).
You could also create a network, where the Master Inverter-Charger was hooked up to the battery store. The AC distribution then could link up buildings spread around the property. E.g. you could have the main battery store & Master Inverter on say a Barn, with the house 100 metres away having a Solar Array on it. The solar would have a Slave Inverter locally, which synced with the existing AC supply and fed power into it at that point in the AC network.
You might turn have a Turbine some distance away on top of a 3rd building - same again - a slave inverter converting the DC into AC, and sharing it onto the AC LAN.
The Master Inverter could bring programmed with load parameters and what level of power to contribute FROM the battery store at loads in excess of the generated power, and to put power BACK when supply exceeded demand.
In addition, you could programme the Master to call upon other AC sources (I.e. Generator or indeed Mains AC) when load exceeded set parameters (to utilise the battery storage for lower level, longer duration base loads only - to utilise the batteries best, and protect them from big discharges & excessive Cycling.
You can program the system to call upon AC source to re-charge the battery store with a proper 3-stage charging cycle (& simultaneously support the demand on the AC LAN) if the battery store became depleted.... and indeed set parameters / preferences for just when the system should use an AC Source (e.g. to take advantage of low-tarriff periods, or to set a "quiet time" when a generator would only be triggered if battery store levels got to the lowest override trigger voltage.
I hope that explains.