Last week we took down my pre-fab concrete section garage.
It was sat on small foundation walls (2 blocks depth) with a soil floor.
Im wanting to put new foundations in, and a concrete slab for the floor, and put the structure back up. Nothing wrong with the old foundation walls at all, but im moving the job by about a foot, so nothing will line up any more.
There was also a path down the side of the garage - about 2" of concrete.
Say i want to put in a 6" base - can i leave the 2" path in place, and put 4" above it? Same with the old foundation walls? Does this create some sort of fixed pivot where cracking will occur?
All existing stuff has been in place since the early 70s and shows no movement, so soil is pretty stable here (a lot of rock mixed in with the soil - no clay)
Thank you.
It was sat on small foundation walls (2 blocks depth) with a soil floor.
Im wanting to put new foundations in, and a concrete slab for the floor, and put the structure back up. Nothing wrong with the old foundation walls at all, but im moving the job by about a foot, so nothing will line up any more.
There was also a path down the side of the garage - about 2" of concrete.
Say i want to put in a 6" base - can i leave the 2" path in place, and put 4" above it? Same with the old foundation walls? Does this create some sort of fixed pivot where cracking will occur?
All existing stuff has been in place since the early 70s and shows no movement, so soil is pretty stable here (a lot of rock mixed in with the soil - no clay)
Thank you.