Hi All,
I know we have good mix of trades on here, hopefully someone familiar with concreting can help me.
I've tried using a couple of online concrete calculators to work out how much All-in I need to order to make a concrete floor.
Length 9.5m, Width 4.3m, Depth 100mm
Total volume 4.085 Cubic Metres <---- (this I am fine with)
Mix amounts required are Cement 1307Kg, All-in 6.81 tonnes or 5 Cubic metres....
How can 5 Cubic metres of All-in make only 4 Cubic metres of concrete ???? WTF ????
I'm obviously being thick here, can someone please explain to me how 5cubes of All-in only makes 4cubes of concrete, so I can be happy that I will order the correct amount of All-in because I don't want to order too little, I don't mind a bit spare but I don't need a couple of tonne spare.
Thanks
I know we have good mix of trades on here, hopefully someone familiar with concreting can help me.
I've tried using a couple of online concrete calculators to work out how much All-in I need to order to make a concrete floor.
Length 9.5m, Width 4.3m, Depth 100mm
Total volume 4.085 Cubic Metres <---- (this I am fine with)
Mix amounts required are Cement 1307Kg, All-in 6.81 tonnes or 5 Cubic metres....
How can 5 Cubic metres of All-in make only 4 Cubic metres of concrete ???? WTF ????
I'm obviously being thick here, can someone please explain to me how 5cubes of All-in only makes 4cubes of concrete, so I can be happy that I will order the correct amount of All-in because I don't want to order too little, I don't mind a bit spare but I don't need a couple of tonne spare.
Thanks