Had my first go at tiling yesterday and happy with the result wasn’t much but probably took me 1.5-2hrs to do! Just got the grouting to do
Going to do the utility this week but I’ve a few things I’d like to figure out first. This is the space to tile:
I want to go up the walls on the sides, a slither under the window sill.
1. I’m unsure if I should go into the window reveal or not?
2. How high should I be going? Can see previously on the left there was maybe 3 rows of tiles, should I catch the sockets? Maybe even the light switch (probably 6 rows)
3. As the tiles are bevelled what’s the method of internal and external corners? It’s almost like I need to mitre the tiles so they fit neatly.
4. Is it inevitable that I’ll end up with a small piece of tile somewhere? With the cooker splashback I laid them out to ensure I didn’t but with the corners it seems like it’s potentially unavoidable
Cheers gents!

Going to do the utility this week but I’ve a few things I’d like to figure out first. This is the space to tile:


I want to go up the walls on the sides, a slither under the window sill.
1. I’m unsure if I should go into the window reveal or not?
2. How high should I be going? Can see previously on the left there was maybe 3 rows of tiles, should I catch the sockets? Maybe even the light switch (probably 6 rows)
3. As the tiles are bevelled what’s the method of internal and external corners? It’s almost like I need to mitre the tiles so they fit neatly.
4. Is it inevitable that I’ll end up with a small piece of tile somewhere? With the cooker splashback I laid them out to ensure I didn’t but with the corners it seems like it’s potentially unavoidable
Cheers gents!