Milkybars
Member
- Messages
- 1,278
- Location
- Essex
So recenlty I had to take down the end wall of the workshop roughly 7.5 x 3 m to enable some building works.
The wall got built back in solid concrete blocks 140 thick 7.3kn on top of engineeing brick up to damp course ..this protudes out on the interior side by circa 75mm
The water staining was caused before guttering and roof could be sealed up correctly, the wall is now consitently dry
The exterior face has been painted (for vanity).
Workshop is a large open area that I do not heat, aside from residual heat from dehumidifer
I need to put a stud wall in front of this new wall ..and this is where i need assistance or verification of my plan.
Current sratergy is to build the stud wall away from the wall due to foootings.
Bottom 2 x 4" fixed to concrete floor and same fixed at the top also fixed back across the void to the wall
Vertical studs on 600 centres and using 100mm thick PIR board foil backed filling the gaps, fitted tightly and foamed where necessary.
The wall covering is planned to be T&G 18mm OSB, this is somewhat an overkill but should be able to fix to it with ease and I am using it for noise reduction as well.
I do not see the point in breathable or non breathable membranes because of the lack of heating. large space and flat warm roof with false ceilings
Nothing will be air tight although the T&G OSB should act as reasonable moisture barrier even before its painted
There will be a fairly large void behind the stud wall and this will not be ventilated ..but any moisture would drop on to the DPM in the worst case senario
The new stud wall will also have a door frame fixed to it to close up the opening above
Hopefully this all make sense and is sensible ...
The wall got built back in solid concrete blocks 140 thick 7.3kn on top of engineeing brick up to damp course ..this protudes out on the interior side by circa 75mm
The water staining was caused before guttering and roof could be sealed up correctly, the wall is now consitently dry
The exterior face has been painted (for vanity).
Workshop is a large open area that I do not heat, aside from residual heat from dehumidifer
I need to put a stud wall in front of this new wall ..and this is where i need assistance or verification of my plan.
Current sratergy is to build the stud wall away from the wall due to foootings.
Bottom 2 x 4" fixed to concrete floor and same fixed at the top also fixed back across the void to the wall
Vertical studs on 600 centres and using 100mm thick PIR board foil backed filling the gaps, fitted tightly and foamed where necessary.
The wall covering is planned to be T&G 18mm OSB, this is somewhat an overkill but should be able to fix to it with ease and I am using it for noise reduction as well.
I do not see the point in breathable or non breathable membranes because of the lack of heating. large space and flat warm roof with false ceilings
Nothing will be air tight although the T&G OSB should act as reasonable moisture barrier even before its painted
There will be a fairly large void behind the stud wall and this will not be ventilated ..but any moisture would drop on to the DPM in the worst case senario
The new stud wall will also have a door frame fixed to it to close up the opening above
Hopefully this all make sense and is sensible ...
