brewdexta
The biggest tool in the box
- Messages
- 5,749
- Location
- UK
The supply up in t'Pennines is up and down like the Assyrian empire. I've seen a nice Lister 3.5KVA gen set with electric start within easy collecting distance, looks to be in very good nick.
But I have a dilemma, I haven't got around to build the plant room around the back of the house yet, that's next years task. This will be the permanent home for the gennie and it is near the outside meter box and consumer unit so I can get the correct change over switch installed.
Last year we were without power for several days during the winter, so no heating, hot water etc. I was working away so the family moved out to the relatives so ideally I need a means of hooking this up before I build the plant room.
The meter box has a manual cut off switch, very handy if your working on the consumer unit. I have 10mm SWA from the consumer unit out to the barn where I could site the gennie. I left a loop of a few metres on the SWA so I could take it into the new plant room when ready.
I now have a separate consumer unit in the barn with an RCD, there is also an RCD on the main house consumer unit feeding the barn which I intended to swap for an MCB but haven't got around to it yet.
Is there a safe and legal way of hooking the gennie up in the barn so I can feed the house/barn if there is a power cut without frying the guys working on the grid? I'm not too bothered about automatic start, nice to have but not important compared to keeping the kids warm when we get snowed in.
I will of course be getting a spark to do this but I thought I would get some info from the brains on the forum first.
Cheers
Andy
But I have a dilemma, I haven't got around to build the plant room around the back of the house yet, that's next years task. This will be the permanent home for the gennie and it is near the outside meter box and consumer unit so I can get the correct change over switch installed.
Last year we were without power for several days during the winter, so no heating, hot water etc. I was working away so the family moved out to the relatives so ideally I need a means of hooking this up before I build the plant room.
The meter box has a manual cut off switch, very handy if your working on the consumer unit. I have 10mm SWA from the consumer unit out to the barn where I could site the gennie. I left a loop of a few metres on the SWA so I could take it into the new plant room when ready.
I now have a separate consumer unit in the barn with an RCD, there is also an RCD on the main house consumer unit feeding the barn which I intended to swap for an MCB but haven't got around to it yet.
Is there a safe and legal way of hooking the gennie up in the barn so I can feed the house/barn if there is a power cut without frying the guys working on the grid? I'm not too bothered about automatic start, nice to have but not important compared to keeping the kids warm when we get snowed in.
I will of course be getting a spark to do this but I thought I would get some info from the brains on the forum first.
Cheers
Andy