julianf
Member
- Messages
- 8,589
- Location
- devon, uk
Ive started a new thread on this one. The old thread outlined the errors, but its clear now that the job needs re-doing.
The original job was min of 4" on top of compacted hardcore, with mesh 2" up from the hardcore (ie a min of 2" from the surface)
Whats there is kind of solid. What i was initially hoping to do was take 2" off the surface, and re-lay that, with another layer of mesh.
But -
mild steel mesh has to be at least 2" from the surface (?)
Im thinking the taking up job becomes a load more difficult if i take out the existing mesh also, but, if it has to be done...
Here is a video of the surface -
http://s1277.photobucket.com/user/j...rete/VID_20150906_184005_zpsa7vawkct.mp4.html
Also, i emptied a barrel of rain water on it the other day... and it hissed / bubbled!
This is for hard standing. Its not going to take traffic of any degree, but i want a good finish for wheeling stuff across it with small castors (engine crane etc).
Would stainless mesh, laid 1" down, in 2" of concrete do the job? Again, what's there is kind of structual.... ish...
The area is 6m x 2.3m and there is no access for ready mix : (
The original job was min of 4" on top of compacted hardcore, with mesh 2" up from the hardcore (ie a min of 2" from the surface)
Whats there is kind of solid. What i was initially hoping to do was take 2" off the surface, and re-lay that, with another layer of mesh.
But -
mild steel mesh has to be at least 2" from the surface (?)
Im thinking the taking up job becomes a load more difficult if i take out the existing mesh also, but, if it has to be done...
Here is a video of the surface -
http://s1277.photobucket.com/user/j...rete/VID_20150906_184005_zpsa7vawkct.mp4.html
Also, i emptied a barrel of rain water on it the other day... and it hissed / bubbled!
This is for hard standing. Its not going to take traffic of any degree, but i want a good finish for wheeling stuff across it with small castors (engine crane etc).
Would stainless mesh, laid 1" down, in 2" of concrete do the job? Again, what's there is kind of structual.... ish...