Been up to check on erection progress a job I drew a while back. They started erecting Monday afternoon and just have the anti sag bars to put in.
Went up easily with no issues , the fabrication was spot on as was the drawing... the erectors even went as far as to say well done ! Lol
There's a double skin ply roof to go on, with tin roof on top of that, all in preparation for the roofing contractor to come in to a lay a grass roof system.
Concrete panels to be mounted to the front, with the bank being reinstated up around 5ft up the front of the concrete panels.
Slab to be poured with a slope to a drain running round the inside of the structure
Few pics , its all shiney shiney for now
And the original model.............
Went up easily with no issues , the fabrication was spot on as was the drawing... the erectors even went as far as to say well done ! Lol
There's a double skin ply roof to go on, with tin roof on top of that, all in preparation for the roofing contractor to come in to a lay a grass roof system.
Concrete panels to be mounted to the front, with the bank being reinstated up around 5ft up the front of the concrete panels.
Slab to be poured with a slope to a drain running round the inside of the structure
Few pics , its all shiney shiney for now
And the original model.............